Industrial Engineering and Production Management - Section 1 (5)

  • Home
  • Mechanical Engineering
  • Mechanical Engineering Q&A
  • Industrial Engineering and Production Management - Section 1
Directions to Solve

Industrial Engineering and Production Management - Section 1

33. 

Probabilistic time for completion of any activity can be found out from

A. optimistic time
B. pessimistic time
C. most likely time
D. all of these

Answer: Option D

Explanation:

No answer description available for this question.

View Answer Discuss Workspace Report

34. 

Which one of the following chart gives simultaneously information about the progress of work and machine loading?

A. Process chart
B. Machine load chart
C. Man-machine chart
D. Gantt chart

Answer: Option C

Explanation:

No answer description available for this question.

View Answer Discuss Workspace Report

35. 

Bar chart is suitable for

A. large project
B. major work
C. minor work
D. all of these

Answer: Option C

Explanation:

No answer description available for this question.

View Answer Discuss Workspace Report

36. 

In a network shown in the below figure, the critical path is along

744-93-1

A. 1-2-3-4-8-9
B. 1-2-3-5-6-7-8-9
C. 1-2-3-4-7-8-9
D. 1-2-5-6-7-8-9

Answer: Option B

Explanation:

No answer description available for this question.

View Answer Discuss Workspace Report

37. 

Fixed position layout is also known as

A. analytical layout
B. synthetic layout
C. static product layout
D. none of these

Answer: Option C

Explanation:

No answer description available for this question.

View Answer Discuss Workspace Report

38. 

The procedure of modifying work content to give more meaning and enjoyment to the job by involving employees in planning, organisation and control of their work, is termed as

A. job enlargement
B. job enrichment
C. job rotation
D. job evaluation

Answer: Option B

Explanation:

No answer description available for this question.

View Answer Discuss Workspace Report

39. 

When slack of an activity is negative

A. it represents a situation where extra resources are available and the completion of project is not delayed
B. it represents that a programme falls behind schedule and additional resources are required to complete the project in time
C. the activity is critical and any delay in its performance will delay the completion of whole project
D. all of the above

Answer: Option B

Explanation:

No answer description available for this question.

View Answer Discuss Workspace Report

40. 

Military type of organisation is known as

A. line organisation
B. functional organisation
C. line and staff organisation
D. line, staff and functional organisation

Answer: Option A

Explanation:

No answer description available for this question.

View Answer Discuss Workspace Report

  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7

Questions & Answers

Aptitude Chemical Engineering Civil Engineering Computer Science & Engineering Current Affairs Data Interpretation Electrical & Electronics Engineering Electronics & Communication Engineering General Knowledge Logical Reasoning Mechanical Engineering Non Verbal Reasoning Verbal Ability Verbal Reasoning

Interviews

HR Interview

Jobs

Sarkari Jobs

Results

Rojgar ResultSarkari Result

Admission

Admission 2023

Admit Card

Admit Card 2023

Answer Key

Answer Key 2023
copyright
Privacy Policy
© 2025 IndiaBIX. All Rights Reserved.

Report