Construction Management - Section 1

  • Home
  • Civil Engineering
  • Civil Engineering Questions and Answers
  • Construction Management - Section 1
Directions to Solve

Construction Management - Section 1

In this portion, there are many questions available to solve
which are related to construction management and every question is important.

1. 

Pick up the correct statement  from the following:

A. CPM analysis is activity oriented
B. PERT analysis is event oriented
C. CPM does not make any allowance for the uncertainties in the duration of time
D. In CPM, the time is related to cost
E. All the above.

Answer: Option E

Explanation:

No answer description available for this question. Let us discuss.

View Answer Discuss Workspace Report

2. 

Modular co-ordination of construction means proper

A. planning
B. designing
C. execution
D. all the above.

Answer: Option D

Explanation:

No answer description available for this question. Let us discuss.

View Answer Discuss Workspace Report

3. 

The Overall in-charge of an organisation at the site responsible for the execution of the works, is

A. Executive Engineer
B. Engineer
C. Junior Engineer
D. Sub overseer
E. Assistant Engineer.

Answer: Option B

Explanation:

No answer description available for this question. Let us discuss.

View Answer Discuss Workspace Report

4. 

If TL is the latest allowable event occurrence time, total activity slack(s), is equal to

A. LST-EST
B. LFT-EFT
C. TL-EFT
D. all the above.

Answer: Option D

Explanation:

No answer description available for this question. Let us discuss.

View Answer Discuss Workspace Report

5. 

The first method invented for planning projects, was

A. Bar chart method
B. Milestone chart
C. Critical path method (CPM)
D. Programme Evaluation and Review Technique (PERT)

Answer: Option A

Explanation:

No answer description available for this question. Let us discuss.

View Answer Discuss Workspace Report

6. 

Bar charts are suitable for

A. minor works
B. major works
C. large projects
D. all the Above.

Answer: Option A

Explanation:

No answer description available for this question. Let us discuss.

View Answer Discuss Workspace Report

7. 

A critical ratio scheduling

A. establishes the relative priorities among various activities on a common basis
B. determines the status of each activity
C. adjusts automatically changes in activity progress
D. is a dynamic system
E. none of these.

Answer: Option E

Explanation:

No answer description available for this question. Let us discuss.

View Answer Discuss Workspace Report

8. 

Works costing less than Rs. 20,000 are treated as

A. projects
B. major projects
C. minor projects
D. all the above.

Answer: Option C

Explanation:

No answer description available for this question. Let us discuss.

View Answer Discuss Workspace Report

  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7

Questions & Answers

Aptitude Chemical Engineering Civil Engineering Computer Science & Engineering Current Affairs Data Interpretation Electrical & Electronics Engineering Electronics & Communication Engineering General Knowledge Logical Reasoning Mechanical Engineering Non Verbal Reasoning Verbal Ability Verbal Reasoning

Interviews

HR Interview

Jobs

Sarkari Jobs

Results

Rojgar ResultSarkari Result

Admission

Admission 2023

Admit Card

Admit Card 2023

Answer Key

Answer Key 2023
copyright
Privacy Policy
© 2025 IndiaBIX. All Rights Reserved.

Report