| 33. | Pick up the correct statement from the following: |
|||||||||
Answer: Option E Explanation: No answer description available for this question. Let us discuss. |
| 34. | The concrete work for the following part of the building of specified thickness is measured in square metres |
|||||||||
Answer: Option E Explanation: No answer description available for this question. Let us discuss. |
| 35. | Pick up the incorrect statement regarding a master trap from the following : |
|||||||||
Answer: Option E Explanation: No answer description available for this question. Let us discuss. |
| 36. | While preparing a detailed estimate |
|||||||
Answer: Option D Explanation: No answer description available for this question. Let us discuss. |
| 37. | The height of the sink of wash basin above floor level is kept |
|||||||
Answer: Option C Explanation: No answer description available for this question. Let us discuss. |
| 38. | In long and short wall method of estimation, the length of long wall is the centre to centre distance between the walls and |
|||||||
Answer: Option B Explanation: No answer description available for this question. Let us discuss. |
| 39. | In case of laying gullies, siphons, intercepting traps, the cost includes |
|||||||
Answer: Option D Explanation: No answer description available for this question. Let us discuss. |
| 40. | Pick up the correct statement in case of water supply. |
|||||||||
Answer: Option E Explanation: No answer description available for this question. Let us discuss. |