IndiaBIX
IndiaBIX
Start typing & press "Enter" or "ESC" to close
  • Home
  • Jobs
  • Results
  • Current Affairs
  • GK
  • Online Test
  • HR Interview
  • BLOG

Building Construction - Section 1 (3)

  • Home
  • Civil Engineering
  • Civil Engineering Questions and Answers
  • Building Construction - Section 1
Directions to Solve

Building Construction - Section 1

building construction section is full of important question which are
asked in this field and you will get these MCQs and can solve to test your skills.

17. 

A projecting piece usually provided to support a truss, is

A. cornice
B. coping
C. frieze
D. lintal.

Answer: Option C

Explanation:

No answer description available for this question. Let us discuss.

View Answer Discuss Workspace Report

18. 

In English garden wall bond

A. one course of headers to three or five course of stretchers
B. queen closer in provided in each heading course
C. the middle course of stretchers is started with a header to give proper vertical joints
D. all the above.

Answer: Option D

Explanation:

No answer description available for this question. Let us discuss.

View Answer Discuss Workspace Report

19. 

During percussion drilling

A. ground water observations are hindered due to entry of the slurry in the soil below the bottom of the hole
B. caving or mixing of strata are caused in soft soils or cohesionless soils
C. the soil to a considerable depth below the bottom of the hole gets disturbed
D. all the above.

Answer: Option D

Explanation:

No answer description available for this question. Let us discuss.

View Answer Discuss Workspace Report

20. 

The angular steps used for changing direction of the stairs, are called

A. round steps
B. angular steps
C. winders
D. radial steps
E. circular steps.

Answer: Option C

Explanation:

No answer description available for this question. Let us discuss.

View Answer Discuss Workspace Report

21. 

The maximum permissible deflection of a timber beam supporting a roof, is

A. L/100
B. L/150
C. L/260
D. L/360
E. none of these.

Answer: Option D

Explanation:

No answer description available for this question. Let us discuss.

View Answer Discuss Workspace Report

22. 

For providing a raft foundation, the following activities are involved

  1. ramming the foundation bed
  2. excavation of the soil upto required depth
  3. laying the reinforcement over the foundation bed
  4. curing the cement concrete placed over reinforcement
  5. pouring the cement concrete over the reinforcement.

The correct sequence is

 

A. 1, 2, 3, 4, 5
B. 5, 4, 3, 2, 1
C. 2, 1, 3, 5, 4
D. 3, 2, 5, 1, 4.

Answer: Option C

Explanation:

No answer description available for this question. Let us discuss.

View Answer Discuss Workspace Report

23. 

In case of multi-storeyed buildings, the forms to be removed first are

A. sides of beams and girders
B. column forms
C. bottom of beams and girders
D. all the above at the same time.

Answer: Option A

Explanation:

No answer description available for this question. Let us discuss.

View Answer Discuss Workspace Report

24. 

The pile which is provided with a bulb filled with concrete at its lower end, is known as

A. Simplex pile
B. Mac-Arthur pile
C. Raymond pile
D. none of these.

Answer: Option B

Explanation:

No answer description available for this question. Let us discuss.

View Answer Discuss Workspace Report

  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7

Questions & Answers

Aptitude Chemical Engineering Civil Engineering Computer Science & Engineering Current Affairs Data Interpretation Electrical & Electronics Engineering Electronics & Communication Engineering General Knowledge Logical Reasoning Mechanical Engineering Non Verbal Reasoning Verbal Ability Verbal Reasoning

Interviews

HR Interview

Jobs

Sarkari Jobs

Results

Rojgar ResultSarkari Result

Admission

Admission 2023

Admit Card

Admit Card 2023

Answer Key

Answer Key 2023
copyright
Privacy Policy
© 2025 IndiaBIX. All Rights Reserved.

Report