A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?

  • Home
  • Aptitude
  • Time and Work
  • Time and Work - General Questions
  • Discuss - 454
1. 

A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?

[A]. 30 days
[B]. 40 days
[C]. 60 days
[D]. 70 days

Answer: Option C

Explanation:

Let A's 1 day's work = x and B's 1 day's work = y.

Then, x + y = 1 and 16x + 44y = 1.
30
Solving these two equations, we get: x = 1 and y = 1
60 60
 B's 1 day's work = 1 .
60

Hence, B alone shall finish the whole work in 60 days.

Workspace Report
Leave a Comment

Aptitude :: Time and Work : More Exercises

  • Time and Work - General Questions

Questions & Answers

Aptitude Chemical Engineering Civil Engineering Computer Science & Engineering Current Affairs Data Interpretation Electrical & Electronics Engineering Electronics & Communication Engineering General Knowledge Logical Reasoning Mechanical Engineering Non Verbal Reasoning Verbal Ability Verbal Reasoning

Interviews

HR Interview

Jobs

Sarkari Jobs

Results

Rojgar ResultSarkari Result

Admission

Admission 2023

Admit Card

Admit Card 2022

Answer Key

Answer Key 2023
copyright
Privacy Policy
© 2023 IndiaBIX. All Rights Reserved.

Report