X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?

  • Home
  • Aptitude
  • Time and Work
  • Time and Work - General Questions
  • Discuss - 452
1. 

X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?

[A]. 13 1/3 days
[B]. 15 days
[C]. 20 days
[D]. 26 days

Answer: Option A

Explanation:

Work done by X in 8 days = 1-sym-oparen-h1 1 x 8 1-sym-cparen-h1 = 1 .
40 5
Remaining work = 1-sym-oparen-h1 1 - 1 1-sym-cparen-h1 = 4 .
5 5
Now, 4 work is done by Y in 16 days.
5
Whole work will be done by Y in 1-sym-oparen-h1 16 x 5 1-sym-cparen-h1 = 20 days.
4
Therefore X's 1 day's work = 1 , Y's 1 day's work = 1 .
40 20
(X + Y)'s 1 day's work = 1-sym-oparen-h1 1 + 1 1-sym-cparen-h1 = 3 .
40 20 40
Hence, X and Y will together complete the work in   40 1-sym-cparen-h1 = 13 1 days.
3 3
Workspace Report
Leave a Comment

Aptitude :: Time and Work : More Exercises

  • Time and Work - General Questions

Questions & Answers

Aptitude Chemical Engineering Civil Engineering Computer Science & Engineering Current Affairs Data Interpretation Electrical & Electronics Engineering Electronics & Communication Engineering General Knowledge Logical Reasoning Mechanical Engineering Non Verbal Reasoning Verbal Ability Verbal Reasoning

Interviews

HR Interview

Jobs

Sarkari Jobs

Results

Rojgar ResultSarkari Result

Admission

Admission 2023

Admit Card

Admit Card 2023

Answer Key

Answer Key 2023
copyright
Privacy Policy
© 2023 IndiaBIX. All Rights Reserved.

Report