Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is:

  • Home
  • Aptitude
  • Time and Work
  • Time and Work - General Questions
  • Discuss - 444
1. 

Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is:

[A]. 15
[B]. 16
[C]. 18
[D]. 25

Answer: Option B

Explanation:

Ratio of times taken by Sakshi and Tanya = 125 : 100 = 5 : 4.

Suppose Tanya takes x days to do the work.

5 : 4 :: 20 : x     x = 1-sym-oparen-h1 4 x 20 1-sym-cparen-h1
5

 x = 16 days.

Hence, Tanya takes 16 days to complete the work.

Workspace Report
Leave a Comment

Aptitude :: Time and Work : More Exercises

  • Time and Work - General Questions

Questions & Answers

Aptitude Chemical Engineering Civil Engineering Computer Science & Engineering Current Affairs Data Interpretation Electrical & Electronics Engineering Electronics & Communication Engineering General Knowledge Logical Reasoning Mechanical Engineering Non Verbal Reasoning Verbal Ability Verbal Reasoning

Interviews

HR Interview

Jobs

Sarkari Jobs

Results

Rojgar ResultSarkari Result

Admission

Admission 2023

Admit Card

Admit Card 2022

Answer Key

Answer Key 2023
copyright
Privacy Policy
© 2023 IndiaBIX. All Rights Reserved.

Report