1. | P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work? |
|||||||||||||||||||||||||||||||||||||||||||||||
Answer: Option A Explanation: P can complete the work in (12 x 8) hrs. = 96 hrs. Q can complete the work in (8 x 10) hrs. = 80 hrs.
|