If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be:

  • Home
  • Aptitude
  • Time and Work
  • Time and Work - General Questions
  • Discuss - 430
1. 

If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be:

[A]. 4 days
[B]. 5 days
[C]. 6 days
[D]. 7 days

Answer: Option A

Explanation:

Let 1 man's 1 day's work = x and 1 boy's 1 day's work = y.

Then, 6x + 8y = 1 and 26x + 48y = 1 .
10 2
Solving these two equations, we get : x = 1 and y = 1 .
100 200
(15 men + 20 boy)'s 1 day's work = 1-sym-oparen-h1 15 + 20 1-sym-cparen-h1 = 1 .
100 200 4

 15 men and 20 boys can do the work in 4 days.

Workspace Report
Leave a Comment

Aptitude :: Time and Work : More Exercises

  • Time and Work - General Questions

Questions & Answers

Aptitude Chemical Engineering Civil Engineering Computer Science & Engineering Current Affairs Data Interpretation Electrical & Electronics Engineering Electronics & Communication Engineering General Knowledge Logical Reasoning Mechanical Engineering Non Verbal Reasoning Verbal Ability Verbal Reasoning

Interviews

HR Interview

Jobs

Sarkari Jobs

Results

Rojgar ResultSarkari Result

Admission

Admission 2023

Admit Card

Admit Card 2022

Answer Key

Answer Key 2023
copyright
Privacy Policy
© 2023 IndiaBIX. All Rights Reserved.

Report