36 men can complete a piece of work in 18 days. In how many days will 27 men complete the same work?
Answer: Option D
Explanation:
Let the required number of days be x.
Less men, More days (Indirect Proportion)
27 : 36 :: 18 : x 27 x x = 36 x 18
x = 24.